Concrete pumps are commonly used in the construction side of a current construction equipment, it can greatly improve the efficiency of construction, welcomed by the construction side. But to extend the service life of concrete pumps, concrete pumps to maintain a certain maintenance skills are very important. So the maintenance of concrete pumps How should it? Specifically from the following aspects.
1, the hydraulic oil
Working medium hydraulic oil as a clean height requirements, hydraulic oil tank can not just kick the cover, which prevents contamination of the hydraulic oil. Need to be reminded that the hydraulic oil should be replaced after the first 300 hours of work, after every 600 hours of work should be replaced once a hydraulic oil, if found in the course of their work with hydraulic oil emulsion, deterioration and other phenomena should immediately replace the hydraulic oil.
2. Thermometer
Under normal circumstances, the thermometer is usually displayed oil hydraulic oil, while the normal working temperature of the hydraulic oil is generally 30 ℃ -60 ℃, the highest oil temperature generally does not exceed 70 ℃.
3, the oil level gauge
Usually the oil level gauge can be used to observe the number of the oil tank, during normal operation the oil level in the oil level gauge must generally be positioned at a predetermined position above the scale, if the lack of hydraulic oil should be added immediately.
4, the drain valve
Use the drain valve is generally open for use when cleaning the tank, usually usually drain valve is closed. After 24 hours a week down the drain valve can be opened once the water tank exclude precipitation in the bottom.
5, the air filter (on the hydraulic tank)
Air filter can prevent outside debris mixed with air filtration is recommended once every six months to replace.
6, high-pressure filter (main boom system with one each)
When the prism pointer finger in the oil filter on the green logo, indicating working properly, the filter is not clogged; when the pointer to the standard yellow color marking to indicate that there is clogging the filter, but can continue to work; when the pointer is pointing to a red logo , indicating serious filter blockage can not continue to work, you must replace the filter immediately, every time you replace the hydraulic oil should also replace the filter.
7, the fastening element
Boot should be checked daily before each fastener is loose, then tighten if loose should be the next steps.
8, cylinder seals
Cylinder seals should work 1000 hours per replacement of cylinder seals once.
9, the electrical components
Boot should be checked daily before each electrical components and wiring is abnormal loose.
10, put the ball valve cylinder head and the upper and lower spherical bearings
Should be checked every 500 hours of work put the ball valve cylinder head and the upper and lower spherical bearings once, if badly worn should be replaced.
Concrete pump is currently a lot of construction side commonly used construction equipment, in daily life for good maintenance of concrete machinery can better extend its life. Through the above description, I believe the majority of users of the concrete pump maintenance skills already know. If you have additional questions, you can visit truemax.cn to learn more about, you can also call our 24-hour toll-free hotline 0086-571-85803511 deeper understanding.
1, the hydraulic oil
Working medium hydraulic oil as a clean height requirements, hydraulic oil tank can not just kick the cover, which prevents contamination of the hydraulic oil. Need to be reminded that the hydraulic oil should be replaced after the first 300 hours of work, after every 600 hours of work should be replaced once a hydraulic oil, if found in the course of their work with hydraulic oil emulsion, deterioration and other phenomena should immediately replace the hydraulic oil.
2. Thermometer
Under normal circumstances, the thermometer is usually displayed oil hydraulic oil, while the normal working temperature of the hydraulic oil is generally 30 ℃ -60 ℃, the highest oil temperature generally does not exceed 70 ℃.
3, the oil level gauge
Usually the oil level gauge can be used to observe the number of the oil tank, during normal operation the oil level in the oil level gauge must generally be positioned at a predetermined position above the scale, if the lack of hydraulic oil should be added immediately.
4, the drain valve
Use the drain valve is generally open for use when cleaning the tank, usually usually drain valve is closed. After 24 hours a week down the drain valve can be opened once the water tank exclude precipitation in the bottom.
5, the air filter (on the hydraulic tank)
Air filter can prevent outside debris mixed with air filtration is recommended once every six months to replace.
6, high-pressure filter (main boom system with one each)
When the prism pointer finger in the oil filter on the green logo, indicating working properly, the filter is not clogged; when the pointer to the standard yellow color marking to indicate that there is clogging the filter, but can continue to work; when the pointer is pointing to a red logo , indicating serious filter blockage can not continue to work, you must replace the filter immediately, every time you replace the hydraulic oil should also replace the filter.
7, the fastening element
Boot should be checked daily before each fastener is loose, then tighten if loose should be the next steps.
8, cylinder seals
Cylinder seals should work 1000 hours per replacement of cylinder seals once.
9, the electrical components
Boot should be checked daily before each electrical components and wiring is abnormal loose.
10, put the ball valve cylinder head and the upper and lower spherical bearings
Should be checked every 500 hours of work put the ball valve cylinder head and the upper and lower spherical bearings once, if badly worn should be replaced.
Concrete pump is currently a lot of construction side commonly used construction equipment, in daily life for good maintenance of concrete machinery can better extend its life. Through the above description, I believe the majority of users of the concrete pump maintenance skills already know. If you have additional questions, you can visit truemax.cn to learn more about, you can also call our 24-hour toll-free hotline 0086-571-85803511 deeper understanding.